Average Cost of a Semi-Detached Extension in 2026 (UK)

A semi-detached house extension costs roughly £2,000–£2,900 per m² in 2026. That puts a typical 20m² single-storey rear or side extension at around £42,000–£58,000, while a full two-storey extension runs £70,000–£120,000+. Because you share a wall and foundations with the house next door, a Party Wall Act agreement is almost always part of the job. The final figure turns on the extension type, glazing, kitchen or bathroom fit-out and your region — here's the full 2026 breakdown.

~£2,000–£2,900/m² 20m² โ‰ˆ £42k–£58k Updated Aug 2026
Get My 3 Free Extension Quotes
60 seconds · No spam · No obligation
Always free for homeowners
Free, no-obligation quotes
You decide who to hire
Cost data across 519 UK towns

Semi-detached extension cost by size — 2026

12m² side infill£26,000–£38,00015m² rear£30,000–£44,00020m² typical£42,000–£58,00025m² large£52,000–£72,000Two-storey£70,000–£120,000London uplift+20–30% on all sizes

Single-storey figures are for a standard, finished specification. Source: BestBuilders 2026 quote data · 519 UK towns

Semi-detached extension cost by size (2026)

SizeTypical cost (standard finish)With premium glazing & fit-out
12m² side infill£26,000–£38,000£40,000–£48,000
15m² rear£30,000–£44,000£46,000–£55,000
20m² (typical rear/side)£42,000–£58,000£60,000–£72,000
25m² (large single-storey)£52,000–£72,000£76,000–£90,000
Two-storey (~40m² over two floors)£70,000–£120,000£125,000–£160,000

Ranges assume a mid-range specification, standard foundations and a straightforward party wall agreement. London and the South-East typically sit 20–30% above these figures; parts of the North and Midlands 5–10% below.

Cost by extension type and region

The extension type you choose on a semi-detached house is usually dictated by where the space is — out the back, into the side passage, or up over the existing footprint. Here's how the common options compare per m² before regional uplift.

TypeCost per m² (2026)Best for
Single-storey rear£2,000–£2,700Kitchen-diner or extra living space — the most common semi extension
Single-storey side infill£2,100–£2,900Widening a narrow galley kitchen into the side passage
Two-storey (side or rear)£1,900–£2,500Adding a bedroom and bathroom above — cheapest per m²
Wraparound (side + rear)£2,200–£3,000The biggest transformation; usually needs full planning

Two-storey work is the cheapest per square metre because you pay once for foundations and roof but gain two floors. Regionally, expect London and the South-East at the top of every range, with the North-East, Yorkshire and much of the Midlands 5–10% below the national figure. Use our extension cost calculator or the double-storey extension calculator for a size- and region-specific estimate.

Where the money goes

ElementShare of budgetNotes
Foundations & groundworks15–20%Rises with poor ground, nearby trees or a shared drain to divert
Structure (walls, steel, roof)30–35%Includes any steel beam for a knock-through to the existing house
Glazing (doors, rooflights)15–25%Bi-folds, sliding doors and lanterns are the biggest single variable
Internal fit-out20–30%A new kitchen or bathroom pushes the top of the range
Fees, regs & party wall5–12%Design, structural engineer, Building Control and the party wall surveyor

What's in the price — and what isn't

A builder's quote for the shell and fit-out usually covers groundworks, structure, roof, plastering, first and second fix, and decoration. What often sits outside the headline figure is where budgets slip:

ItemTypical cost (2026)Included as standard?
Kitchen units & appliances+£8,000–£25,000Rarely — priced separately
Bi-fold or sliding doors (3m)+£2,500–£5,500Often an upgrade line
Roof lantern (1.5m x 1m)+£1,500–£3,000Upgrade
Structural steel & knock-through+£1,500–£4,000Sometimes included — always confirm
Party wall surveyor+£700–£2,000No — see party wall surveyor costs
Architect / technician drawings£1,200–£3,500No — see architect costs
Skip hire & waste removal+£400–£1,200Usually included — confirm
Removing an existing garage or lean-to+£800–£3,000No, if the site needs clearing first

Always ask whether the quote is for the shell only or a fully finished room, and whether the kitchen, flooring and decoration are inside or outside the figure. That single question explains most of the gap between two quotes.

How long a semi-detached extension takes

  1. Weeks −6 to 0 — survey, drawings, structural calculations, planning check, party wall notice served and Building Regs submission.
  2. Weeks 1–3 — groundworks: footings dug and poured, any shared drain diverted, slab laid.
  3. Weeks 4–8 — walls up, steels in, roof on, weathertight.
  4. Weeks 9–12 — glazing in, first-fix electrics and plumbing, insulation, plasterboard.
  5. Weeks 12–18 — plastering, floors, second fix, decoration, snagging and Building Control sign-off.

A single-storey rear or side extension is typically 12–18 weeks on site; a two-storey extension runs 16–24 weeks. Start the party wall process early — serving notice about two months before work protects the programme.

How much value it adds

A well-built extension on a semi-detached home usually adds value, but rarely more than it costs in cash terms — the real return is the extra usable space. As a rough guide, a kitchen-diner rear extension can add 5–12% to a home's value, and an extra double bedroom with a bathroom from a two-storey extension often adds 10–15%, subject to the local ceiling price for the street. Overspending past what the best house on the road sells for is the most common way to lose money. Check recent sold prices for extended semis nearby before you commit to a premium specification.

Planning permission, party wall and building regulations

Planning permission. Many single-storey rear extensions on a semi fall under permitted development — up to 6m deep under the prior-approval Larger Home Extension scheme, or 3m without it, within height limits. A single-storey side extension can be permitted development only if it's no more than half the width of the original house and under 4m high; anything wider, or any two-storey side extension, normally needs a full application. A wraparound almost always does. Confirm before you design — see planning guides for a side extension, rear extension and two-storey extension.

Party Wall Act. Because a semi shares a wall and often foundations with the attached property, you'll almost certainly need to serve a party wall notice on your neighbour and, if they dissent, appoint a surveyor. Budget £700–£2,000 and start about two months ahead.

Building regulations. Every extension must meet Building Regs for structure, insulation, fire safety, drainage and ventilation, regardless of planning. Your builder works to approved drawings and a Building Control inspector signs off the key stages — keep the completion certificate for when you sell.

Choosing the builder: your checklist

  • Ask for two recent semi-detached extensions you can visit or phone the owners about — not just general building work.
  • Ask to see public liability insurance and check it's current and adequate for the contract value.
  • Check whether they belong to a trade body such as the FMB, and verify membership on the FMB register yourself.
  • Get a written stage-payment schedule — never more than 10–15% up front — and a fixed programme.
  • Agree who serves the party wall notice and who pays the surveyor.
  • Get three itemised quotes on identical drawings so the numbers are genuinely comparable.

Where the budget goes wrong

  • Glazing chosen late — bi-folds and a lantern can add £8,000 to a £45,000 job. Price them at design stage.
  • Shared drain discovered on site — a manhole or sewer in the footprint costs £800–£2,500 to divert or build over. A pre-build drainage check removes the surprise.
  • Party wall left too late — serving notice after work starts can stop the job for weeks.
  • Kitchen budget forgotten — the build price rarely includes the kitchen going in it.
  • No contingency — hold 10–15% back for what the ground reveals.

FAQs

Roughly £2,000–£2,900 per m². A typical 20m² single-storey rear or side extension is around £42,000–£58,000, while a two-storey extension runs £70,000–£120,000 or more.
Many single-storey rear extensions are permitted development within size limits. A side extension usually needs planning if it's more than half the width of the house or over 4m high, and two-storey or wraparound extensions normally need a full application. Check with your local planning authority.
Almost always. A semi shares a wall and often foundations with the attached house, so you'll usually need to serve a party wall notice on your neighbour and, if they dissent, appoint a surveyor. Budget £700–£2,000 and start about two months before work.
Usually, though rarely more than it costs in cash. A kitchen-diner rear extension can add around 5–12%, and an extra bedroom with a bathroom 10–15%, up to the ceiling price for your street. Avoid overspending past the best house on the road.

Get 3 Free Semi-Detached Extension Quotes

BestBuilders matches you with up to 3 vetted UK builders. Compare fixed-price extension quotes on the same spec — free, with no obligation to accept.

Get My 3 Free Extension Quotes
60 seconds · No spam · No obligation
Get My Free Quotes →
Reviewed by the BestBuilders editorial team on 20 August 2026 ยท Next scheduled review: November 2026 ยท See our editorial standards and how we get paid.