How-To Guide ยท Updated May 2026 ยท Real UK Build Times

How Long Does a Kitchen Extension Take in 2026? UK Timeline

Most UK kitchen extensions take 6 to 9 months end-to-end in 2026. Of that, only 12โ€“22 weeks is on-site building โ€” the rest is design, planning and lead times. This guide breaks it down week by week so you can plan around school terms, supplier holidays and the inevitable โ€œkitchen unusable for 6 weeksโ€ period.

Real UK build durations ยท 519 towns
Updated May 2026
FMB / TrustMark builders
Free quotes — no obligation

Kitchen Extension Timeline by Type

Side-Return
Filling the alley ยท Single storey
12 โ€“ 16 weeks on-site

8โ€“10 wk design + planning, then 12โ€“16 wk build. Easiest type โ€” short spans, no major foundations.

Single-Storey Rear
Full-width ยท 4-6m projection
14 โ€“ 20 weeks on-site

10โ€“12 wk planning, 14โ€“20 wk build. Standard knock-through, long RSJ, large patio doors.

Wraparound
Side + rear combined
18 โ€“ 26 weeks on-site

12โ€“16 wk planning, 18โ€“26 wk build. Two facades, more glazing, deeper foundations.

Standard 5x4m Single-Storey Rear Extension — Full Timeline

A realistic 30-week timeline for a standard rear kitchen extension under Permitted Development. Add 8–12 weeks if full planning permission is required.

PhaseWeeksActivity
Design1โ€“4Architect brief, measured survey, draft plans, refinement
Lawful Dev / Planning5โ€“12Submit LDC (PD) or full planning. 6โ€“8 wk decision, often longer
Building Regs & structural10โ€“16Structural calcs, energy calcs, full plans submission, tender
Tender & appoint builder14โ€“183 quotes, references, contract (JCT Minor Works), payment schedule
Site set-up & demolition18โ€“19Skip, scaffold, demolition of rear wall / outbuilding
Foundations19โ€“21Trench dig, BC inspection, concrete pour, beam-and-block
Walls & structure21โ€“24Brick & block walls, RSJ install, lintels, insulation cavity
Roof & weather-tight24โ€“26Flat roof / pitched, lantern or glass roof, doors, weather seal
First fix M&E + plaster26โ€“27Electrics, plumbing, UFH, plasterboard, plaster skim, drying
Kitchen install27โ€“28Cabinets, worktops (templated after install), appliances
Second fix & decoration28โ€“29Tiling, flooring, switches/sockets, painting, sealing
Snagging & sign-off29โ€“30Building Control completion cert, snag list, final payment

Why UK Kitchen Extensions Run Late โ€” and How to Avoid It

Top 6 causes of delay (2026 data)

  1. Planning over-runs โ€” council backlogs, average 9-13 weeks vs target 8
  2. Steel fabrication lead times โ€” 6-10 weeks for engineered RSJs
  3. Window/door lead times โ€” 8-14 weeks for aluminium bifolds & lanterns
  4. Client variations mid-build โ€” each adds 1-3 weeks
  5. Kitchen lead time mismatch โ€” cabinets arrive before plaster dries
  6. Drainage diversions โ€” SuDS / sewer build-over consents

How to keep things on schedule

  • Submit LDC the moment plans are finalised
  • Order steel and glazing the day planning is granted
  • Lock the kitchen design before strip-out โ€” no mid-build changes
  • Use a JCT contract with liquidated damages clause
  • Schedule the kitchen install for week +1 after plaster dry
  • Keep the family out of the build for 4-6 weeks (rentals, family stay)

Get Quotes from FMB Builders Who Hit Deadlines

The single biggest predictor of finishing on time is choosing the right builder. BestBuilders matches you with FMB or TrustMark UK builders, with verifiable references on past kitchen extensions — and JCT contracts as standard. Up to 3 free quotes within 24 hours.

โœ“ FMB / TrustMark / NHBC builders only
โœ“ Up to 3 quotes within 24 hours
โœ“ No obligation, no spam
Takes 60 seconds ยท No spam ยท No obligation

Common Questions About Kitchen Extension Timelines

How long does a single-storey kitchen extension take to build?

A standard 5x4m single-storey rear extension takes 14โ€“20 weeks on-site in 2026, plus 12โ€“20 weeks of design and planning beforehand. End-to-end: 6โ€“9 months from first architect meeting to handover.

How long does a side-return extension take?

Side-return extensions (filling in the alley alongside a Victorian terrace) take 12โ€“16 weeks on-site โ€” the quickest type because spans are short and foundations modest. Add 8โ€“10 weeks for planning approval.

How long does a wraparound kitchen extension take?

A wraparound (side + rear) extension takes 18โ€“26 weeks on-site, plus 12โ€“16 weeks for planning. Two facades, more glazing and deeper foundations push the timeline; expect 7โ€“11 months end-to-end.

How long does planning permission take for a kitchen extension?

Statutory determination is 8 weeks but most UK councils now run 9โ€“13 weeks in 2026 due to backlogs. Lawful Development Certificates (PD) typically come back in 6โ€“8 weeks. Add 21 days neighbour consultation in either case.

Can I live in the house during a kitchen extension build?

Yes for most of the build, but expect the kitchen to be unusable for 4โ€“8 weeks during knock-through, plastering and install. Most homeowners set up a temporary microwave kitchen in another room or move out for the toughest 3-4 weeks.

What is the longest part of a kitchen extension build?

Lead times beat on-site work for length โ€” steel fabrication (6โ€“10 weeks), aluminium bifolds and lantern roofs (8โ€“14 weeks) and bespoke kitchens (8โ€“16 weeks) frequently outrun the build. Order them the day planning is granted.