Fixed Price vs Cost Plus Builder Contracts (2026 UK Guide)
UK extension builders quote in two fundamentally different ways: fixed price (you agree one number for the whole job) or cost plus (you pay materials + labour at cost + a margin, typically 12โ20%). Fixed price gives you certainty but bakes in a 10โ18% โrisk premiumโ โ the builder's protection against unknown ground conditions, material price moves, and scope creep. Cost plus is leaner and more transparent but transfers cost risk to you: budget overruns hit your wallet, not the builder's. This guide shows when each model wins, the contract clauses to insist on, and a real ยฃ68k Bristol extension priced both ways.
Planning the work? Check what it usually costs, or work out your own estimate. The free quote form is at the top of this page.
Fixed price vs cost plus โ which is right for you?
- Choose fixed price if you want budget certainty, the design and spec are fully resolved before signing, and you'd rather pay a 10โ18% premium than face overrun risk.
- Choose cost plus if you trust the builder, your spec will evolve (heritage, period property, design-led project), and you can absorb 10โ25% overruns without it derailing the project.
- Hybrid โtarget costโ models (most JCT IC 2016/24 contracts) split overrun pain and gain between you and the builder โ typically the best middle ground above ยฃ80k project value.
Fixed Price vs Cost Plus โ The Eight Differences That Matter
Worked example (illustrative): Bristol Single-Storey Rear Extension Priced Both Ways
25mยฒ single-storey rear extension, mid-range spec. Same builder, same brief, same March 2026 start. Here's how each contract played out.
Fixed Price quote
- Builder absorbed a ยฃ2,800 steel-price rise (good for owner)
- Owner requested an island upgrade mid-build โ ยฃ6,200 variation order
- Final cost: ยฃ84,600 (variation only)
Cost Plus quote
- Actual material cost ran ยฃ71,200 (ยฃ3,200 over due to steel rise)
- Owner upgraded kitchen island mid-build at cost โ no premium
- Final cost: ยฃ86,900 (ยฃ75,500 actual ร 1.15)
Verdict: Without the kitchen upgrade, cost plus would have come in at ยฃ82,000 โ saving ยฃ2,600 vs fixed. With it, both landed within 3% of each other. The decision came down to risk appetite: fixed price felt safer; cost plus felt more honest.
Common Questions
Related Guides
More comparison and decision guides to help you pick the right builder and contract.
How to Hire a Trusted Bathroom Fitter
Vetting questions, red flags and the documentation to insist on before signing.
Read Guide โUK House Extension Cost 2026
Full framework for budgeting any UK extension โ rear, side, wrap or two-storey.
Read Guide โAll Comparison Guides
Side-by-side breakdowns to help you make confident decisions on builders, materials and spec.
Browse Compare โ